Wednesday, September 2, 2009

Big update

We were surprised to find that they have installed the power dome today. This is after telling me that they would not be able to bring forward the date so we were expecting Tuesday next week. Just need them to now connect the other end and energise the dome!

Tuesday, September 1, 2009

Small update

Informed the builder today that the dome was not installed on Friday and asked them what their plan is? Reminded the contracts administrator (don't know where our construction coordinator is) that they could use a generator to get the brickies going. The response; bricking will start on Monday using a generator until the power is put in.

Again, wait and see if this happens!

Monday, August 31, 2009

Update...well no update

Well the power did not go in on Friday. Nothing happened to day. So no update. Did go to the slab over the weekend and the kids swept the slab and I swept the footings ready for the bricking to go up. Kinda opptomistic wasn't it?
Called Power Alliance and they again said 8 August to get the dome installed and the 10 August to get it energised. So much for the builder saying last Friday!