Tuesday, February 16, 2010

Telstra Connection

The telstra connection has been organised for tomorrow. Hopefully he will not disturb the flooring guys when they are sanding. Let's see if the conduit has been put in properly!

Construction continues

Well, we picked up our keys on Friday. It was not a fancy affair which took just 15 minutes. Our CC ran through a folder of stuff of information and a box of towels as a gift. We got two sets of keys each on Ultimate Homes keyrings so we don't have to cut additional ones. Our CC asked if we would be going straight to the house and Bec said no. I think this did not impress our CC but in our defence we have a builders key and the floorboards and patio is underway so there is still construction at the house so it is not as if we could sit in the house and postulate. Any so the flooring people have now laid all the timber and should be back later this week to sand. Then they will be back next week to polish and then we have to wait another week before we can get in to walk and put furnitue in - so it will be at least 3 March before we move! :( The patio was also completed today. It looks great and once we get the liquid limestone under it, there will be a lot of space for the kids to play. I think they will love it. We have booked the limestone for the 2nd and 3rd March as this is the earliest that they can do it.
The crossover application to City of Stirling came back with a fail. The crossover does not meet their specifications and our CC is looking into this for us.