Thursday, November 26, 2009

Floor heating installed

Bathroom floor heating installed today. Looks like this is the last thing that will happen this week. So hopefully screeding next week!
Didn't see any signs of the plumber but I guess he will only be back once the bench tops and basins are in so that he can complete all the sanitary plumbing.

Ensuite
Bathroom
Ensuite toilet (one of the luxuries)

Sanitary Plumbing Day 2

Well the plumber was back again today. He has finished the relocation of the powder room water and drain connections. In doing so he has punched through to the other room (bed 5). So more render and float set repair needed.
He has also relocated the cold water point for the fridge from the cupboard next to the rangehood to the cupboard next to the cooktop. This is per the addenda and plans however this means more repair to the render and float set. This should not be too bad as it will be covered by the glass splashback.
Also noticed in the WIR for bed 2 that the render and float set needs to be repaired. This would have been damaged when he repaired the copper pipes for the hot water system.
Looks like the tiler has also been today. He has done some prep work in the powder and laundry. He has drawn the line where the tiles go to and removed the float below that. Also the floor has been swept nicely to allow for the screed.






Wednesday, November 25, 2009

Sanitary Plumbing

The plumber was back today. So the list of items completed today
1. Another half load of brickie sand delivered
2. Hot water pipe in kitchen that was punctured is now repaired and rendered over! Hmmm how was it fixed?
3. Bath is installed.
4. Floor waste drain piping completed
5. Roof vents installed
6. Garage wall to slab gap cemented
7. Copper pipes for gas boost HWS re-installed. Water reconnected permanently.
8. Powder room taps and waste drain relocated to suit the shrouded basin that we selected.


Garage wall to slab cement
Roof mushrooms
Bath installed
Chrome floor grille
Floor waste drains
Sewer vent?
Repaired hot water pipe in kitchen (rendered already)
Powder room plumbing relocated

Tuesday, November 24, 2009

Cabinets installed / Tiles delivered

Well, firstly good news is that the cabinet maker was back to install the cabinets. We also got our tiles and tapware. However on the negative side, they broke one of the bed 1 windows and the cabinet maker put one of the fixing screws through the hot water pipe in the kitchen.

Kitchen

Ensuite
Bathroom
Laundry Hole put in the hot water pipe Broken window
Tiles

Monday, November 23, 2009

Cabinets Delivered!

Doesn't seem like there was any work today however we had another delivery - the cabinets were delivered. We also got one bath, one hand basin and some more internal timber. Can't wait until they install them.

Ensuite (one half)
Ensuite (other half)
Bathroom
Laundry
Kitchen
Back of kitchen cupboards
Powder basin
Bath
Kitchen through the window


Kitchen through the window