Wednesday, December 23, 2009

Final kitchen cupboard

More work today. The final kitchen cupboard was installed. This was the one that had to wait for the kitchen bench as it sits on top of the bench. It was not complete though as the fill bits to cover between the top and bulkkhead is not yet installed. So it looks odd but it is in.

The plasterer has also come back to patch the glass splashback area and touched up some spots in bed 1 and also the passageway. This is over the top of our nice first coat and sealer. Hope the painter reseals those patches!



Tuesday, December 22, 2009

Woohoo work during the "break"

Well we get some work done over the break! There was someone at the house yesterday as there is now a new sign up in the study window. Today they cleaned the fence!



Monday, December 21, 2009

Paint colours

OK before we forget the paint colours are

Bed 1/Study/Library/Home theatre is Solver Clipper Race
Main house is Solver Seagull
Boys room is Solver Rhapsody
Girls room is Fantasy Fair
Front render is Solver Smooth Cream
Eaves is Solver Talc
Door frames and doors is Solver Simply White
Front door is Solver Talc

Someone was at the house today. Bec said that there is a new sign in the study window but no other sign of work. So we'll see what happens tomorrow.