Thursday, December 10, 2009

More tiling

The tiler was back today. He was working alone again. The bathroom is almost complete. Still have the laundry, ensuite and powder to go.


Wednesday, December 9, 2009

Update

OK so lots have happened in the last week since I have been away. The painter is now well progressed although some things look like they need another coat. He has also sealed our walls and will be back to paint them shortly. Bec has selected all the colours.

The tiler is continuing after his holiday to Broome. Most of the floor tiles are done and he has started on the bathroom wall tiling. So maybe another week for him to finish which puts it just before the Christmas break.

The front fence is now done including letterbox. The pillars are placed where I wanted them. So basically the first infill frames the front door, then the next infill frames the study, then the bedroom.

The ensuite and bathroom benchtops went in today including the basins. The zuchero seems more white than what we remembered but it still looks good. Not sure when the kitchen benchtop will go in as we only selected that middle of last week. The kitchen sink is delivered and waiting to be installed.

Bec also saw the glass splashback van (Five Star Splashbacks) so presumably they came to measure up. Maybe this will go in next week.









Sunday, December 6, 2009

Haven't been past the house for a couple of days :) However had a call from the tiling man and he wants to meet tomorrow morning just to go over the fine details. Then off to bunnings to buy the letterbox for tuesday.