Wednesday, December 23, 2009

Final kitchen cupboard

More work today. The final kitchen cupboard was installed. This was the one that had to wait for the kitchen bench as it sits on top of the bench. It was not complete though as the fill bits to cover between the top and bulkkhead is not yet installed. So it looks odd but it is in.

The plasterer has also come back to patch the glass splashback area and touched up some spots in bed 1 and also the passageway. This is over the top of our nice first coat and sealer. Hope the painter reseals those patches!



Tuesday, December 22, 2009

Woohoo work during the "break"

Well we get some work done over the break! There was someone at the house yesterday as there is now a new sign up in the study window. Today they cleaned the fence!



Monday, December 21, 2009

Paint colours

OK before we forget the paint colours are

Bed 1/Study/Library/Home theatre is Solver Clipper Race
Main house is Solver Seagull
Boys room is Solver Rhapsody
Girls room is Fantasy Fair
Front render is Solver Smooth Cream
Eaves is Solver Talc
Door frames and doors is Solver Simply White
Front door is Solver Talc

Someone was at the house today. Bec said that there is a new sign in the study window but no other sign of work. So we'll see what happens tomorrow.

Friday, December 18, 2009

Final Day of Work for 2009

Well today was the last day of work officially for the builder. The painters were back to give the doors a final coat. It looks like they have also given some rooms another coat but hard to tell. They have given the front render another coat and it looks fabulous! Now we can really see how the front of the house will look as they have removed the protective film from the front door glass. Now we are just waiting for the plumber to do his thing....I wonder if he will work over the break? I wonder if there will be ANY work over the next two weeks!



Thursday, December 17, 2009

More painting

The painter came back today to do another coat for the door frames and also painted the front render. Now I know why they have not cut in around the door frames! (because they had not done the final coat on the frames).



Tiling Complete

Tiling is complete however the bigger news is that the kitchen bench is finally installed! So photos of the progress to date.

First coat of paint in the girls rooms
First coat of paint in the boys room
First coat of paint in bedroom
Ensuite shower
Ensuite toilet
Ensuite
Kitchen with benchtop
More kitchen
Dishwasher recess and sink
Hotplate and oven
Bathroom
Bathroom floor
Powder
Powder
Laundry - wasn't expecting the tiling on this wall so bonus
Laundry
Laundry bench

Wednesday, December 16, 2009

Tiling complete

Tiling almost complete today. The laundry is now complete with grout. So is the powder room. So is the bathroom. The ensuite and toilet is complete except for the grouting. The kitchen sill is almost done except for one tile at the appliance cupboard end - they will probably wait until the cupboard is installed before installing the last tile. The cupboard can't go on until the bench is on. The tiler's son said the bench is likely to be installed on Friday.

So hopefully by Christmas we will have everything done except the final plumbing, final electrical, roller door, soakwell plumbing, grate and sump to front of garage, paving, final painting. Oh and the downpipes by the foyer.

Tuesday, December 15, 2009

Floor heating broken!

The floor heating in the ensuite was broken! :( Not sure if it was the plumber or tiler. It looks like the drain pipe was not long enough so they had to replace it with a longer piece which meant that they had to dig into the slab! arghhhhhhhh

We noticed it on Friday afternoon. We thought that this would delay them because the repair would need to be done by the heating company but alas it was repaired by Monday morning. Tuesday the screeding was done and the tiles replaced!

They can move to fix the problem. I wonder if they will tell us or hope that they fixed it before we noticed it!

Broken!
Fixed Done

Long time between updates

It has been a while but life has been hectic after coming back from China. The builder is still working and hoefully some work will be done over the shutdown period. However a lot has happened in the last week. Mostly it has been tiling but the plumber looks like he has come also. The painter has been and gone.

Tiling: ensuite is finished (except grout), ensuite toilet walls to be done, bathroom is finished (grouting done on walls), laundry is done, powder is done, kitchen is started - well the one row of tiles along the window!.

Painter: vents on roof painted, eaves done, downpipes done, ceilings done, walls sealed and first coat applied. We are getting him to paint the internal as well for a handsome cash sum.

Plumber: cut the cupboards in preperation for the sink drains. Gas plumber has installed the gas point in the alfresco.

Cabinet maker: reinstalled cupboard next to rangehood - he even replaced the back so that there is no hole from the old water tap point.

Benchtops: bathroom and ensuite benchtops are installed. Waiting for the kitchen Corian (which we signed off as variation 9).

Powder water and drain connection
Powder from the door
Powder room room from the laundry
Skirting tile in the walk in linen
Tiling behind the washing machine
Laundry
Ensuite shower step
Ensuite shower
Ensuite shower
Bathroom
Bathroom shower
Bathroom from door

Bathroom with grouting on the wall tiling

Thursday, December 10, 2009

More tiling

The tiler was back today. He was working alone again. The bathroom is almost complete. Still have the laundry, ensuite and powder to go.