Thursday, June 4, 2009

One step forward, two steps back

Everything seems to happen when I am overseas. The prestart person called today to say that the council has faxed them to say that the building license can not be submitted until the demolition license has been submitted. So after landing in Schipol, I called the council to check what is the procedure now and they said no, same old procedure. So called the demolition company and asked them to go and submit the license tomorrow. The council also said that there is an issue with the home theathre. She said that the builder needs to show how they intent to meet the requirements for ventilation and light. I mentioned that there is a note on the drawing that addresses this but I guess that was being too cheeky.

The good news is that the variations from pre-start are ready. They are posting it so we should have them by tomorrow.