Another very productive day today. They have now finished off the roof tiles by mortoring the ridge caps in. So I guess we will get the next progress payment invoice for roof cover.
Inside the render blokes got a lot done today. All the rear living areas (games, meals, family and kitchen) are now done. They also did the home theatre so that is a lot of walls rendered today. So much so that they needed another lot of sand.
Our CC telephoned today to give us an answer to the two questions posed. The bathroom light will be changed to the low voltage downlight (on a separate switch) and also the SS will check about the linen/broom cupboard ceiling height. The render is only to 25c but we expect 31c.
Tuesday, October 27, 2009
Monday, October 26, 2009
Render float - Day 3
Another productive day even though we had a bit of rain. It seemed to rain lightly all day. The guys did the float in beds 2 and 3. Also the bedroom corridor has been done.
Also unusual was that they did the family room wall (opposite the linen cupboard) and also the rear wall for the fridge recess. They must have had some left over and did these small areas.
Also unusual was that they did the family room wall (opposite the linen cupboard) and also the rear wall for the fridge recess. They must have had some left over and did these small areas.
Friday, October 23, 2009
Thursday, October 22, 2009
Float started
We had some people on site today. They started the float! Seemed like they only worked half a day however they are cleaning the rooms as they go and also removing the door frame stiffeners. So Joshua and Sophie's room was done today. They look like they have swept the laundry/powder ready to do the float tomorrow. They have also done some prep work for the bathroom conduit.
On another note, the plumber has permanently connected the water now. I gues he had the access to sink the pipe. Other work was that the work was removed from the site today so it is clean except for the sand piles.
Bec noted how long it took to get from the back of the house to the front (as Sophie wanted to wee so she had to run from the back to the car at the front.

On another note, the plumber has permanently connected the water now. I gues he had the access to sink the pipe. Other work was that the work was removed from the site today so it is clean except for the sand piles.
Bec noted how long it took to get from the back of the house to the front (as Sophie wanted to wee so she had to run from the back to the car at the front.
Wednesday, October 21, 2009
Render sand
Tuesday, October 20, 2009
Site Clean #2
Not a very productive day. They needed to clean up the pile of rubbish as it has grown very big. So they cleaned up the site again. This is the second site clean. Also a pile of sand was dropped, not a very big one so not sure if they don't use as much sand for the float as they do bricking but they know what they are doing!
Also picked up today that the sparky has missed one light switch. Easy to miss as we have 2 lights in the bathroom - one for the room and one over the basin. We have the lights on separate switches but I think he has added them together. Will email the CC tomorrow and see what they have to say.
Also picked up today that the sparky has missed one light switch. Easy to miss as we have 2 lights in the bathroom - one for the room and one over the basin. We have the lights on separate switches but I think he has added them together. Will email the CC tomorrow and see what they have to say.
Site before clean
Site after clean
Monday, October 19, 2009
Waiting for render
Well nothing happened Friday and today. Was not expecting anything on Friday but had hoped that they would deliver sand for the render but alas it was not to be. Still there was someone at the house today as they water house from the meter to the house was disconnected. Apart from that nothing else appears to have happened.
Waiting for tomorrow.
Waiting for tomorrow.