Saturday, October 10, 2009

Roof tiles delivered! Photos

OK so here are the photos from Friday. A lot of progress so don't know where to start. Electrical chasing now complete - they had to come back for the ones they missed and to change a couple. Plumbing day 2 and a lot of the chasing is now done. Holes drilled for the external taps so now we have a good idea of their location. They have put them through from the internal wall. They have chased on our front bedroom wall and down through the footings at two locations. Took us a while to figure what these were for but we believe that one is for the incoming water and one for the incoming gas. Kinda makes sense.
Also the roof tiles and battens were delivered! So the SS was dead on when he said 9th October a couple of weeks ago when we met him.
Also drove past the block today (Saturday) and the plumber was working! He worked the whole day as he was still there at 4pm!


No comments: