Friday, September 11, 2009

Bricking Day 4

Again the weather was gusting and the rain was torrential but intermitent. The brickies were there again today and got a lot of work done seeing as they had to assembly the scaffold to reach the top of the walls. They have now put all the windows in and have 90% of the lintels in above the windows. This would take a lot of time as they have also put the water protection above the windows too. So the back and front internal walls are to plate height. All the external walls are to 19c. They have done the garage/library wall and this makes the house start to look like a house when viewed from the street.
Ensuite window and toilet window
Front internal wall to plate height

Front elevation

Rear interal wall to plate height

Library/garage wall and garage entry door to the right